Bartın Çimento cement plant - a new production capacity.

In April 2012, Belim Makina completed the installation of a new burning line of 3000 t/d capacity at the Bartın Çimento cement plant in Turkey. After one month of operation in the complete production cycle a 48-hour test run was staged, and all the parameters of the process, as guaranteed by IKN, which was responsible for the design of the whole burning line, were reached. In addition, IKN provided the basic components such as exhaust fans, valves, flue dampers, kiln drives, kiln girth gear, rollers and a clinker cooler.
Author: F. Lichomski