Advanced technology for the new kiln line at Qizilqum Sement

During the productivity improvement of the AO Qi­zilqum Sement (Uzbekistan) plant a decision was made to design and produce a new kiln line capable of producing 5,500 tpd of clinker. All the components supplied by IKN (Germany) under an EPC contract allow to realize latest technologies of cement production. Start­up of the kiln line is scheduled by the beginning of 2022.