AO Sebryakovcement: technical re-equipment continues

AO Sebryakovcement continues a large-scale technical re-equipment of its production capacities. The reconstruction of the process line No. 8 of the combined method of cement clinker production with its transfer to the dry technology began. The construction of a new cement mill No. 14 working in a closed cycle together with a clinker primary crusher is underway. Preparations are being made to create an automatic system for monitoring industrial emissions.