The second cement production line of OOO YUGPK in Novotroitsk commissioned.

In August 2013 tests to validate the performance guarantees under the contract between South Ural Mining and Processing Company (OOO YUGPK) and ZAB Zementanlagenbau GmbH Dessau were successfully completed. The contract was for equipment supply and engineering services for the project to build a second dry process cement production line with a capacity of 3,000 tpd of clinker in Novotroitsk.
Author: A.V. Dianov, O.V. Dubinin, D. Wetzel, E.V. Schegolyaev