Gallantt Industry Pvt. Ltd orders Gebr. Pfeiffer ready2grind grinding plant

Gallantt Industry Pvt. Ltd has ordered its first ready2grind compact plant for the Indian subcontinent. The plant with MVR 2500 C-4 will be installed in the company’s Gorakhpur factory.

The mill capacity is 65 tph at an average product fineness of 3750 cm²/g according to Blaine. Due to the planned installation in the vicinity of a steelworks, blast furnace slag, steelworks slag from an induction furnace and fly ash from an in-house power plant will also be considered as supplementary cementitious materials (SCM) addition to clinker and gypsum.

The mill will be equipped with a 1270 kW main drive and an integrated SLS 2650 VC high-performance classifier of the latest generation.

Apart from the core components of the MVR mill, which are supplied by Gebr. Pfeiffer from Germany, the other components of the ready2grind plant are supplied by Gebr. Pfeiffer (India) Pvt. Ltd, a 100 % subsidiary in the Gebr. Pfeiffer Group.

In addition to the support of the customer during the processing of the order by the engineers of Gebr. Pfeiffer, the Customer Service Centre in Noida is available to the customer, as a competent contact partner for all aftersales questions both remotely and in real terms by sending personnel to the plant.
Region: India
Tags: production
The use of materials published on the site is allowed only with the reference to the source (the journal «Cement and its application») and a hyperlink to the quoted material.
Share:  
The use of materials published on the site is allowed only with reference to the source (the journal «Cement and its application») and a hyperlink to the quoted material.
© 2007-2024 PetroCem Ltd
Privacy policy